Week 14: All the Finishing Touches

Week 14. The end of the tunnel (well for phase one of the house plan at least). The house remodel has finally come to its end and we are ready to start moving in! This past week all of the finishing touches of the house got complete. I know that I have said a few times that this place is actually starting to look like a home but it really feels like home now. The transformation is just unbelievable. Matt and I are still pinching ourselves. I cant believe all of the work we have done over the past 3 months, I cant believe the amount of work and how fast we accomplished it. It is all just surreal and we cant wait to be in our home.

So all of those finishing touches...

The HVAC system got the full clean out and boy was it filthy. When I walked in the house after the clean out it actually smelled so fresh and so clean. The smell of dust and paint has started to diminish. A big shout of to Jim Golden and his crew for doing a fantastic job! Of course that was the easy part of it. The fun didn't begin until we had to start putting back on the new vents and return grills. Of course the house being as old as it is all of the openings were different lengths and heights and they just don't seem to make them the way they used too. We did get lucky on a few of them but majority we have to do some minor handy work to get the fit just right. Glen, the master trim work man, had to hand cut almost every single vent (22 total) to have the new grills fit right. A couple of them he had to build out like case work and they all turned out looking fantastic.

Both the master and bedroom 1 closets' dimensions were changed so we had some holes in the hardwood floors in these spaces. To get it to match up we would have had to lay all new hardwood so our second best option was to carpet these. Remember that newly laid carpet the was in the Knotty Pine room, the one we rolled up and stored in the basement to reuse? Well it is just enough to carpet the stairs to the basement and both closets. Depending on what we use for the flooring in the basement this is a great temporary fix to dress up the stairs and have a finish look when looking down for the first floor.

 Before: Basement stairs

 Before: Basement stairs
 
 After: New carpet stairs

 After: New carpet stairs

The master closet also got finished up this week with hanging the new rods and shelving units. I went with the standard white wire shelving units in here and they turned out looking good.

After: New walk-in & carpet

The master shower got it's new glass door with chrome hardware to match the rest of the room. We splurged here and went with the dual direction swinging hinges. In the small space it really does help out because you can open the door into the shower vs. towards you so when one is brushing their teeth at the sink you wont be in each others way.

 After: Master shower door


The most exciting part this week was having our granite installed! I went back and forth and back  and forth on 2 selections of granite for about a week and I am so very  happy I went with my gut. It is absolutely stunning. Not to toot my own horn again but toot, toot. Our kitchen looks amazing and the cost of it all was so well worth it because it Is where you spend the majority of your time.

 After: New kitchen granite


I know that I am little late on this post but we have been super busy moving and trying to get settled in. We have gotten pretty far in the kitchen, bedrooms and baths. We still have boxes to unload, mainly home décor, wall art, window treatments, etc and that is going to take time to figure where I want to put everything again. We also need to buy a new kitchen table and some more seating for the knotty pine room along with many other things to fill this new big home. In this case you just have to take on one thing at a time.

Look out for next week I am going to have lots of pictures of all the rooms once we go through all of our boxes and crates. It is all just so exciting :)

Comments

Popular posts from this blog

#DEMODAY Phase II

Yes #demoday Phase II because like I mentioned we are basically building a new house. After the back was torn down and cleaned up a mini digger was brought in to build out our trenches where the new foundation was going to be poured. The existing slab of concrete where the breezeway and garage sat was kept since the new foot print was larger and it wasn't going to interfere (there was a small part of me that was going to miss the black & red tile floor). Also it was helpful that the team was working on that vs dirt and rock. Trenches were dug so concrete could be poured for the foundation and footers. During the design phase Matt and I went round and round on whether the new addition floor should be the same height as the existing or if we should do a sunken great room. There were benefits to each, mainly a sunken great room would allow for a higher ceiling height and potential for vaulted ceilings. We ultimately decided the entire first floor should be on the same walki...

Week 2: Demo Begins

The framers are here! The framers are here! And boy were the fast. Lonnie and his team took two and a half days for this to happen. Never thought it would be that quick! They did a fantastic job and also learned that he has done work on a few other houses in the neighborhood. Apparently in the 50s and 60s Homerama took place here. Mud/Entry: The wall separating this room from the kitchen and dining room was removed, since it was load bearing we had to install a 14' LVL beam for the proper support. Some people do not like to have this installed when going for an open concept because your ceilings will not be one continuous plane. In our case we are leaving the parallel wall that separates the kitchen/dining and living room which is also load bearing so it is going to match up making it look as if the house was originally built that way.  Before   Before: The Beautiful Knotty Pine Room    After     After   They s...

Week 3: Demo Continues

WEEK 3: DEMO CONTINUES..... Before I can start on what took place this week I have to share a special moment that happen on Monday. So Matt and I are woke up early by our GC letting us know he is going to start on the basement gut that day. Of course this was planned to not happen until Wednesday so for me not to be present when this went down made me quite nervous. But we trust our GC and know he is making the right decisions for us. Matt and I were getting phone calls left and right about this and that all day and when I finally leave from work at the end of the day to head over to the construction zone needless to say I was stressing a little. I am looking around inspecting and see a small piece of paper just sitting on the bar in the basement among some tools and materials. I glance at it thinking it might have been another found surprise in the walls, and boy was it. I immediately asked Lonnie where he got it and answered 'in the crawl space when we ...